Project Results by SEI Level
|
Calendar |
Effort |
Total cost (US$ 000) |
||
SEI level |
time (months) |
(Person months) |
(median) |
(lowest) |
(highest) |
I |
29.8 |
593.5 |
5,440 |
1,786 |
101,721 |
II |
18.5 |
143.0 |
1,311 |
962 |
1,732 |
III |
15.2 |
79.5 |
728 |
518 |
933 |
IV |
12.5 |
42.8 |
392 |
279 |
502 |
For the code and test phases only
of a typical 200,000-line business application.
Project Results by SEI Level
(cont.)
|
Calendar |
Effort |
Defects |
Total cost |
|
SEI level |
time (months) |
(Person months) |
Discovered |
Shipped |
US$ 000 |
I |
29.8 |
593.5 |
1,348 |
61 |
5,440 |
II |
18.5 |
143.0 |
328 |
12 |
1,311 |
III |
15.2 |
79.5 |
182 |
7 |
728 |
IV |
12.5 |
42.8 |
97 |
5 |
392 |
Defect counts include all phases up to final customer shipment.